New timetable AnNa Deliverables

on .

The AnNa Project Board and Consortium meetings in 2015 updated the timetable of the AnNa work.

 The new timetable is presented hereunder. 

Activities

Activity Name

Start Date

PREVIOUS
End Date

NEW
End Date

Milestone

Activity 1

Master Plan 2015

24/01/2012

28/02/2015

01/11/2015

 

Sub-activity 1.1

Functional and Technical Requirements

24/0/2012

30/11/2013

30/11/2013

3

Sub-activity 1.2

Interim Master Plan 2015

24/01/2012

30/11/2013

30/11/2013

5

Sub-activity 1.3

Master Plan 2015 

01/11/2013

28/02/2015

01/11/2015

12

           

Activity 2

Pilots

24/01/2012

15/02/2015

31/12/2015

 

Sub-activity 2.1

Pilot Definition and Prototyping

24/01/2012

31/05/2014

31/12/2014

4

Sub-activity 2.2

Pilot Implementation

24/01/2012

15/02/2015

31/12/2015

11

Sub-activity 2.3

Pilot global features

01/01/2014

31/12/2014

15/02/2015

9

           

Activity 3

Master Plan “Extended Collaboration” (post-2015)

01/09/2013

31/12/2015

31/12/2015

 

Sub-activity 3.1

Framework Master Plan post-2015

01/09/2013

30/06/2014

15/02/2015

8

Sub-activity 3.2

Transport and Logistics, Trade facilities

01/01/2014

31/05/2015

31/07/2015

13

Sub-activity 3.3

Master Plan Extended Collaboration - Project book

01/01/2015

31/12/2015

31/12/2015

16

           

Activity 4

Consultation Panel (Platform)

01/01/2013

15/11/2015

15/11/2015

 

Sub-activity 4.1

Stakeholder 2010/65/EU strategy

01/01/2013

15/12/2013

15/12/2013

6

Sub-activity 4.2

Interaction and commitment

01/01/2013

31/10/2015

31/12/2015

14

Sub-activity 4.3

Final Event

01/01/2014

15/11/2015

31/12/2015

15

           

Activity 5

Project Management

24/01/2012

31/12/2015

31/12/2015

 

Sub-activity 5.1

Project management

24/01/2012

31/12/2015

31/12/2015

1,7, 10

Sub-activity 5.2

Dissemination

24/01/2012

31/12/2015

31/12/2015

2

Sub-activity 5.3

National Coordination and Project Management

24/01/2012

31/12/2015

31/12/2015